The organization of mobile production of LGS framework of the building on the construction site

A three-storey building with a total area of 1750 m2 was produce directly on the construction site using a mobile CNC machine LGS. The framework of the building was produced for 2 weeks.

The production was started in July. People were placed in a finished building in late September of the same year. The assembly of the frame of the building was carried out by the Customer's employees, since the assembly of frameworks made on CNC machines resembles a lego-kit. We as producers provided chief control. This method of production and construction significantly shortened the time and finish cost for Customer.










As well as buildings for workers with using the system Double Wall LGS